BEACONSFIELD GOLD MINE, TASMANIA.
While HVE were undertaking routine oil testing of the mine's transformers it was discovered the mine's only transformer powering the crusher and part of the refinery plant had oil results showing extremely high moisture and dissolved gas levels (63 ppm moisture) and extremely low di-electric strength.
HVE was able to despatch equipment and personnel to Tasmania with 24 hours to undertake remedial works. Oil was treated online for a 24 hour period to lower moisture levels, allowing crushing to commence, and a further 24 hours of online treatment were completed to bring the oil well within the Australian Standards.
Additional works were undertaken comprising the provision and fitment of a larger capacity silica gel filter to better address the mine's method of operation. Beaconsfield Gold have granted permission to display the oil report data showing both before and after oil treatment information - click on the adjacent file to see results.